The City Council has approved a $2.15 million extension of 76th Street from 12th Avenue to Cedar Avenue, which will complete the west-east portion of the Three Rivers Trail through Richfield.

The project approved by the Council Monday night includes:
- Concrete sidewalk on the south side
- Boulevards and boulevard trees
- Three Rivers Park Regional Trail on north side
- On-street concrete bike lanes
- A two-lane asphalt roadway

At the same time, the council approved a five-year street reconstruction plan that will allow it to issue bonds to pay for major street projects without assessing adjacent homeowners and businesses.

They include:
76th Street East (2012)
Richfield Parkway Connection (2013)
North Richfield Parkway between 63rd and 65th streets (2013-14)
66th Street between Upton Avenue to Richfield Parkway (2015)
Portland Avenue from 62nd to 77th Street (2016)

 

facebookcomment

Top City Paychecks

The City of Richfield's three highest paid employees for 2012:
$141,086.40 - City Manager Steve Devich
$121,492.80 -
Public Works Director Mike Eastland
$121,492.80 -
Public Safety Director Barry Fritz
Source: City of Richfield Website

Login Form